Completed Park District Projects
Dugout and Backstop Replacement
Project: Replacing backstop and dugout and fence down the foul line on field #7.
Starting: December 2018
Completion: Projected completed early 2019
Price: $41,547
Electric City Water Park Bathhouse
Project: Renovation of interior and exterior of ECWP facility. ADA upgrades of interior.
Starting: Architectural design - November 2018
Construction - Early 2019
Completion: Completed Summer 2019
Price: Park District $320,724 and CDBG $364,499
Park District Project - Gibson Park Restrooms
Gibson Park Restrooms Restoration
Project: Updating and expanding existing restrooms
Starting: October 2019
Completion: Completed February 2019
Price: $98,008
Girl Scout House Roof in Gibson Park
Project: Replacement of Roof
Starting: March 2020
Completion: Completed March 2020
Price: $14,055
Multi Sports Field #6
Project: Replacing backstop and dugout and fence down on the foul line on field #6.
Starting: Fall 2019
Completion: Projected completed Spring 2020
Price: $20,000 Park District and $18,429 Confero
Jaycee Park
Project: Tennis Courts to pickleball with sidewalk. Reconstructing the basketball court and adding new sidewalk. Pavilion with sidewalk.
Starting: April 2020
Completion: Projected Summer 2020
Price: Budgeted $268,148
Gibson Park Trail & Basketball Court and Elks Riverside Trail Replacement
Project: Replacement of Front Half of Gibson Park Trail, Gibson Park Basketball Court Resurface, and Complete Replacement of Elks Riverside Trail.
Starting: April 2020
Completion: Summer 2020
Price: Park District $340,540 and CDBG $137,500
Grande Vista Park Play Structure
Project: New Play Structure with inclusive features and ADA sidewalk.
Starting: Summer 2020
Completion: Summer 2020
Price: Budgeted cost $64,783
Forestry Equipment
Project: Purchase of Forestry Equipment.
Starting: December 2019
Completion: Ongoing
Price: $259,000
Oddfellows Park Restroom Replacement
Project: Oddfellows Park Restroom Replacement
Starting: Summer 2020
Completion: Projected Summer 2020
Price: Budgeted $250,000
Grande Vista Trail and ADA Sidewalk to Play Structure
Project: Overlay of existing trail. Installation of ADA sidewalk to play structure.
Starting: Summer 2021
Completion: Fall 2021
Price: $101,000 (Estimated Cost)
Multi Sports Field #8
Project: Replacing backstop and dugout and fence down the foul line on filed #8.
Starting: Spring 2021
Completion: Spring 2021
Price: $35,000
Multi Sports Field #5
Project: Replacing backstop and dugout and fence down the foul line on filed #5.
Starting: Spring 2021
Completion: Spring 2021
Price: $35,000
Gibson Pond Wall Project: Repair to wall.
Starting: Spring 2021
Completion: Summer 2021
Price: $185,000
Lions Park Restroom
Project: Lions Park Restroom Replacement
Starting: Summer 2021
Completion: TBD
Price: $200,000 (Estimated cost)
Irrigation Upgrades
Project: Converting existing irrigation systems from manual operation to automatic.
Starting: Summer 2019
Completion: Ongoing
Price: Combined Year 1 and 2 Budgeted Cost $290,000
Tree Replacement
Project: Replacement of trees lost due to disease and weather
Start: Fall 2020
Completion: Ongoing
Price: Budgeted $30,000
Lions Court Overlay
Project: Overlay of Lions Courts.
Starting: Summer 2021
Completion: Summer 2022
Price: $75,000 (Estimated Cost)